Progress on the site in 2008 |
 |
|
| March 2009 |
 |
| July 2008 |
 |
-
The concrete floor slab has been poured for the lower section of level 1, adjoining Liverpool St, and half of the upper section at the rear of the building.
-
Erection of the scaffolding on the lower section of level 1 , to support the formwork for pouring the level 2 concrete floor slab, is almost complete and has been started on the upper section.
-
There is a 1.9 metre height difference between the floor levels of the upper and lower sections of level 1. This will be resolved for level 2 and upward by having a high ceiling in the lower section of level 1, which is why the formwork scaffolding is so high.
-
The two lift shafts can be seen in the middle and top left corner of the photo. The rear ‘goods’ lift shaft is up to level 5 of the 5 levels, which gives an idea of the overall height of the building, however there will be another level above the roof of the building to house the mechanical plant.
-
In the foreground of the photo you can see some of the internal precast concrete wall panels that form feature walls around the auditorium.
|

|
|
| |
| June 2008 |
 |
|
|
 |
 |