Progress on the site in 2008

| Progress Current | Progress Archives | History & Heritage Archaeology | Downloads | Contact Us | Home |
March 2009
march 2009
July 2008
july progress

  • The concrete floor slab has been poured for the lower section of level 1, adjoining Liverpool St, and half of the upper section at the rear of the building.
  • Erection of the scaffolding on the lower section of level 1 , to support the formwork for pouring the level 2 concrete floor slab, is almost complete and has been started on the upper section.
  • There is a 1.9 metre height difference between the floor levels of the upper and lower sections of level 1.  This will be resolved for level 2 and upward by having a high ceiling in the lower section of level 1, which is why the formwork scaffolding is so high.
  • The two lift shafts can be seen in the middle and top left corner of the photo.  The rear ‘goods’ lift shaft is up to level 5 of the 5 levels, which gives an idea of the overall height of the building, however there will be another level above the roof of the building to house the mechanical plant.
  • In the foreground of the photo you can see some of the internal precast concrete wall panels that form feature walls around the auditorium.

 

 

july progress

july progress
 
June 2008
May 2008 - Progress

  • Below ground construction of the  footings has continued. 
    The precast concrete panel  construction of the first two levels of the two l ift shafts  can be seen in the foreground and top left corner of the photo.  
    The lower section of level 1,  adjoining Liverpool  St, is being leveled ready for pouring of the  concrete floor slab.
  • The Photo of Hollydene House shows  some of the less appropriate 20th Century additions to the building have begun  to be removed, revealing the 1825 façade, as the first step in its  redevelopment process.  There is a Conservation Management Plan and the  building is not being demolished.  Later works will re-instate a  front garden and picket fence. In the longer term the project team will  consider how to best reinstate a verandah on the front.  This work will  happen in stages and it is recognised that this may make the building look  ‘unfinished’ during this interim stage of restoration. 
APRIL 2008
Although there doesn’t appear to be much change visible, a lot of work has taken place under the ground to construct the footings to support the new building.  Most of the footings are 900mm diameter holes bored approximately 10 meters into the ground.  Approximately half of these 37 bored piers have been completed.
 
Some of the long coils of steel reinforcing that go into the bored pier holes can be seen laying on the ground in the middle of the photo.
 
Other strip footings and retaining walls have also been constructed.
 
So far approximately 600 tonnes of concrete has been poured.
 
The two Lift shaft bases have been constructed – the main one can be seen in the foreground of the photo.  Each of these lift bases contains approximately 3 tonnes of reinforcing steel and 50 tonnes of concrete as they will act as anchors for the building.
 
Construction of the concrete wall panels has commenced off site.   The first ones will be for the lift shafts and will be brought to site and erected in a few weeks.  
 
The photo also shows the base for tower crane, which has been anchored into the ground.